A start-up plant scheduled to grow from 3 lines to 8, on 24/7

A start-up plant scheduled to grow from 3 lines to 8, on 24/7

HP Hood

Food & Beverage

3 to 8

production lines, scheduled for 24/7 growth

150 to 340+

headcount plan

12-hr

EOWO schedule

The problem

HP Hood's new Batavia, NY plant needed to move from 5 days a week to 24/7, more than double its lines, and hire to match. Employees had been working at least 6 days a week with significant overtime.

What we did

  • Ran confidential surveys so employees could shape and select their schedules
  • Identified the preferred balanced, 4-crew, 12-hour, every-other-weekend-off schedule
  • Provided best practices for overtime, time off, relief staffing, and flexibility
  • Planned a phased transition starting with the half-gallon milk lines in October 2019

The results

  • 3 to 8 production lines planned on the new schedule
  • 150 to 340+ employee growth path
  • Overtime costs dropped dramatically and production steadily increased
  • High engagement and climbing retention
Their (Coleman's) solution delivered a great balance between our employee preferences and our growing business needs.

Mike Corporon, Plant Manager, HP Hood